Site survey — can this room host a liquid cabinet?

Before any vendor call, walk the room with this survey. Five of the six items kill micro-DC liquid deployments in rooms that "look fine": floor, power, heat egress, water, access, noise. Every item links to the math or the check that settles it.

#CheckPass conditionTool / formula
1Floor loadingAs-built slab rating ≥ filled rack print (often 7+ kN/m²)Floor loading calc + structural sign-off
2ElectricalFeed capacity ≥ IT × 1.2 + AC; redundant path or UPS as requiredTDP → rack kW
3Heat egress (L2A)Room AC ≥ 1.1 × IT with margin, air path in/out of the cabinet row1.1× rule + worked guide
4Water (L2L only)Facility loop capacity, temperature class and quality documentedW-class lookup
5Access & deliveryDoor widths, lift capacity, corridor turns for a ~1 t crate on a palletMeasure on site; photograph the worst turn
6NoiseRoom/adjacent use compatible with fan and pump noise at full loadAsk vendor for full-load dBA at 1 m; check room use
FIG. 1 — The six-point survey. Items 1, 3 and 5 fail most often in offices and clinics.

Climate check

Room design temperature drives capacity: an L2A cabinet rated at 25 °C air delivers roughly half at 35 °C (approach temperature). In the tropics the survey includes the room's worst-case temperature with AC failure margins — see hot & tropical climates.

Red flags

  • "The floor is raised, so it's data-center grade" — raised ≠ reinforced. Get the as-built rating.
  • "We'll add AC later" — the day-one AC is what the cabinet derates against. Size now (calculator).
  • Untested condensation margin — cold coolant below room dew point sweats onto live hardware; verify supply temperature vs worst-case dew point.

Related

Room load calculation · RFQ scope checklist · Commissioning

Sources

Survey structure from this site's engineering pages; thresholds link to the formula pages where each number comes from. Nothing on this page replaces a licensed structural and electrical review.